1 00:00:02,250 --> 00:00:12,350 [Music] 2 00:00:17,450 --> 00:00:15,080 Saturn five quarterly film report number 3 00:00:23,440 --> 00:00:17,460 15 covers progress during the period 4 00:00:29,620 --> 00:00:27,010 [Music] 5 00:00:31,720 --> 00:00:29,630 at launch complex 39 of the Kennedy 6 00:00:33,910 --> 00:00:31,730 Space Center where assembly and rollout 7 00:00:36,210 --> 00:00:33,920 of the Saturn 5 facility's checkout 8 00:00:38,799 --> 00:00:36,220 vehicle was accomplished last quarter 9 00:00:40,630 --> 00:00:38,809 checkout of launch facilities and ground 10 00:00:42,850 --> 00:00:40,640 support equipment in connection with the 11 00:00:47,200 --> 00:00:42,860 vehicle was in progress throughout the 12 00:00:49,150 --> 00:00:47,210 report period on June 17th a check-out 13 00:00:51,700 --> 00:00:49,160 milestone was reached with manual 14 00:00:54,189 --> 00:00:51,710 loading of rp1 fuel into the vehicles 15 00:00:56,229 --> 00:00:54,199 first stage the objective was to 16 00:00:58,240 --> 00:00:56,239 checkout loading equipment prior to 17 00:01:00,490 --> 00:00:58,250 testing of the computerized automatic 18 00:01:04,630 --> 00:01:00,500 mode which will be used for flight 19 00:01:06,670 --> 00:01:04,640 stages in mid-july the mobile service 20 00:01:09,370 --> 00:01:06,680 structure which is used primarily for 21 00:01:11,830 --> 00:01:09,380 servicing the Apollo spacecraft was 22 00:01:14,260 --> 00:01:11,840 moved to pad a for mating tests with 23 00:01:17,980 --> 00:01:14,270 paired facilities and then returned to 24 00:01:20,170 --> 00:01:17,990 its parking area for pressurization 25 00:01:22,330 --> 00:01:20,180 tests two operational levels were 26 00:01:25,840 --> 00:01:22,340 performed on all of the Saturn vehicles 27 00:01:28,510 --> 00:01:25,850 propellant tanks to verify LC 39s ground 28 00:01:32,730 --> 00:01:28,520 pressurization system tests were 29 00:01:35,859 --> 00:01:32,740 successfully concluded on August 12th a 30 00:01:38,289 --> 00:01:35,869 rupture of pair days liquid oxygen feed 31 00:01:40,899 --> 00:01:38,299 line between storage tank and replenish 32 00:01:43,810 --> 00:01:40,909 pump during a pump chill down on August 33 00:01:45,489 --> 00:01:43,820 19th caused postponement of a scheduled 34 00:01:48,010 --> 00:01:45,499 series of loading tests with the 35 00:01:50,679 --> 00:01:48,020 cryogenic fuels LOX and liquid hydrogen 36 00:01:53,169 --> 00:01:50,689 an investigation is underway to 37 00:01:54,880 --> 00:01:53,179 determine cause of the accident which is 38 00:01:57,760 --> 00:01:54,890 expected to delay the facilities 39 00:01:59,410 --> 00:01:57,770 checkout program by about a month since 40 00:02:01,660 --> 00:01:59,420 the second stage of the facility's 41 00:02:04,779 --> 00:02:01,670 checkout vehicle will later be used in 42 00:02:14,089 --> 00:02:04,789 the dynamic test vehicle at MSFC the 43 00:02:18,890 --> 00:02:16,819 in first-stage grounds test operations 44 00:02:21,229 --> 00:02:18,900 the upper assembly of the structural 45 00:02:24,199 --> 00:02:21,239 test stage comprising the header tank 46 00:02:26,390 --> 00:02:24,209 locks tank and forward skirt underwent 47 00:02:28,580 --> 00:02:26,400 successful structural testing in the 48 00:02:32,839 --> 00:02:28,590 Marshall centers load tests tower in 49 00:02:34,940 --> 00:02:32,849 late July post firing checkout of the 50 00:02:38,839 --> 00:02:34,950 first flight stage which began last 51 00:02:40,699 --> 00:02:38,849 quarter was completed August 10th the 52 00:02:43,429 --> 00:02:40,709 stage was loaded aboard the barge for 53 00:02:47,720 --> 00:02:43,439 Sidon on August 27th for shipment from 54 00:02:49,759 --> 00:02:47,730 Marshall to KSC a single acceptance 55 00:02:52,250 --> 00:02:49,769 static firing of the second flight stage 56 00:02:55,250 --> 00:02:52,260 was conducted on June 7th in Marshalls 57 00:02:57,379 --> 00:02:55,260 ecstatic test stand after refurbishment 58 00:02:59,990 --> 00:02:57,389 post barring checkout started August 59 00:03:06,020 --> 00:03:00,000 11th with completion due in early 60 00:03:07,909 --> 00:03:06,030 November at Marshalls Michou assembly 61 00:03:09,800 --> 00:03:07,919 facility in New Orleans post 62 00:03:11,990 --> 00:03:09,810 manufacturing checkout of the third 63 00:03:14,179 --> 00:03:12,000 flight stage was completed in late 64 00:03:16,580 --> 00:03:14,189 August by the stage contractor the 65 00:03:19,099 --> 00:03:16,590 Boeing Company the stage will be shipped 66 00:03:22,999 --> 00:03:19,109 to MSFC next quarter for acceptance 67 00:03:25,069 --> 00:03:23,009 static firing horizontal installation 68 00:03:27,110 --> 00:03:25,079 has been completed by Boeing Michou on 69 00:03:30,219 --> 00:03:27,120 the fourth flight stage post 70 00:03:33,020 --> 00:03:30,229 manufacturing checkout is in progress 71 00:03:34,999 --> 00:03:33,030 the fifth flight stage is in the process 72 00:03:38,659 --> 00:03:35,009 of vertical assembly with completion 73 00:03:40,550 --> 00:03:38,669 scheduled for September structural 74 00:03:43,399 --> 00:03:40,560 assembly of major components for the 75 00:03:45,199 --> 00:03:43,409 sixth flight stage and fabrication of 76 00:03:48,550 --> 00:03:45,209 components for the seventh and eighth 77 00:03:51,080 --> 00:03:48,560 flight stages are also underway 78 00:03:53,270 --> 00:03:51,090 installation of a second large boring 79 00:03:55,699 --> 00:03:53,280 mill at Michou for use in Saturn 80 00:03:58,129 --> 00:03:55,709 fabrication work was accomplished in 81 00:04:00,080 --> 00:03:58,139 June obtained from the Watertown 82 00:04:02,149 --> 00:04:00,090 Massachusetts Arsenal for the cost of 83 00:04:04,670 --> 00:04:02,159 dismantling shipping and reassembling 84 00:04:13,290 --> 00:04:04,680 the boring mill has the capability of 85 00:04:18,720 --> 00:04:16,590 repairs 2s2 stage static test stands 86 00:04:21,240 --> 00:04:18,730 number a two at Marshalls Mississippi 87 00:04:24,360 --> 00:04:21,250 test facility were completed in early 88 00:04:27,030 --> 00:04:24,370 August the stand had been damaged May 28 89 00:04:29,700 --> 00:04:27,040 when the s two all system stage was 90 00:04:31,770 --> 00:04:29,710 destroyed due to over pressurization of 91 00:04:34,800 --> 00:04:31,780 the liquid hydrogen tank during a leak 92 00:04:36,900 --> 00:04:34,810 check test program impact was minimized 93 00:04:41,640 --> 00:04:36,910 to do two expeditious handling of 94 00:04:43,140 --> 00:04:41,650 required repairs systems check out of 95 00:04:46,860 --> 00:04:43,150 the initial flight stage was completed 96 00:04:48,600 --> 00:04:46,870 on July 16th by the s2 contractor the 97 00:04:51,270 --> 00:04:48,610 space and Information Systems Division 98 00:04:55,200 --> 00:04:51,280 of North American Aviation at its seal 99 00:04:57,240 --> 00:04:55,210 Beach California facility official 100 00:04:59,640 --> 00:04:57,250 turnover of the stage to NASA was on 101 00:05:01,260 --> 00:04:59,650 July 27th and the stage was shipped 102 00:05:04,290 --> 00:05:01,270 three days later aboard the transport 103 00:05:08,040 --> 00:05:04,300 Point Barrow bound for MTF for 104 00:05:10,170 --> 00:05:08,050 acceptance firing there the first flight 105 00:05:12,510 --> 00:05:10,180 stage arrived on August 12th at the 106 00:05:14,730 --> 00:05:12,520 Michou facility in New Orleans where it 107 00:05:18,180 --> 00:05:14,740 was transferred to a barge for the short 108 00:05:21,060 --> 00:05:18,190 trip to MTF the stage was offloaded at 109 00:05:25,710 --> 00:05:21,070 MTF ss2 vehicle service building the 110 00:05:28,020 --> 00:05:25,720 next day on August 19th the stage was 111 00:05:30,150 --> 00:05:28,030 installed in the a2 test stand and 112 00:05:32,700 --> 00:05:30,160 preparations got underway for static 113 00:05:35,400 --> 00:05:32,710 firings of which a minimum of two are 114 00:05:37,350 --> 00:05:35,410 scheduled in late September after post 115 00:05:38,460 --> 00:05:37,360 firing check out the stage will be 116 00:05:43,200 --> 00:05:38,470 shipped to KSC 117 00:05:45,510 --> 00:05:43,210 in November meanwhile at S&I DCO beach 118 00:05:47,550 --> 00:05:45,520 manufacturing facility systems 119 00:05:50,160 --> 00:05:47,560 installation on the second flight stage 120 00:05:53,130 --> 00:05:50,170 was completed and systems checkout began 121 00:05:55,230 --> 00:05:53,140 on July 23rd following completion of 122 00:05:58,400 --> 00:05:55,240 checkout in late September the stage 123 00:06:00,780 --> 00:05:58,410 will be shipped to MTF in October 124 00:06:03,020 --> 00:06:00,790 vertical assembly of the third flight 125 00:06:05,340 --> 00:06:03,030 stage was finished in early July 126 00:06:07,380 --> 00:06:05,350 hydrostatic testing had been completed 127 00:06:10,050 --> 00:06:07,390 by late August and systems installation 128 00:06:12,870 --> 00:06:10,060 is underway with completion due in 129 00:06:15,180 --> 00:06:12,880 October vertical assembly of the fourth 130 00:06:17,909 --> 00:06:15,190 flight stage started in July and is due 131 00:06:19,680 --> 00:06:17,919 to be finished in September fabrication 132 00:06:21,510 --> 00:06:19,690 and sub assembly of structural 133 00:06:25,560 --> 00:06:21,520 components for the fifth flight stage 134 00:06:26,910 --> 00:06:25,570 are in progress starting firing of the 135 00:06:28,950 --> 00:06:26,920 s2 battleship tests 136 00:06:31,980 --> 00:06:28,960 stage was resumed in June at North 137 00:06:34,110 --> 00:06:31,990 Americans Santa Susana tests ain't due 138 00:06:37,050 --> 00:06:34,120 to the loss of the all system stage at 139 00:06:39,690 --> 00:06:37,060 MTF additional firings of the battleship 140 00:06:41,970 --> 00:06:39,700 with flight hardware incorporated for 141 00:06:45,480 --> 00:06:41,980 deems necessary to enhance stage 142 00:06:47,880 --> 00:06:45,490 maturity for full duration firings were 143 00:06:49,980 --> 00:06:47,890 conducted during the quarter and firings 144 00:06:52,110 --> 00:06:49,990 are scheduled to continue on a minimum 145 00:07:01,110 --> 00:06:52,120 sustaining effort phases through 146 00:07:03,210 --> 00:07:01,120 December post firing checkout was 147 00:07:05,220 --> 00:07:03,220 performed during the report period and 148 00:07:07,590 --> 00:07:05,230 the first flight stage which had been 149 00:07:09,720 --> 00:07:07,600 acceptance fired last quarter at Douglas 150 00:07:12,690 --> 00:07:09,730 aircraft companies Sacramento California 151 00:07:16,850 --> 00:07:12,700 test site the stage was shipped to KSC 152 00:07:19,650 --> 00:07:16,860 by super guppy aircraft on August 12th 153 00:07:21,840 --> 00:07:19,660 the second flight stage arrived at SAC 154 00:07:24,000 --> 00:07:21,850 tow on June 1st from da C's 155 00:07:26,880 --> 00:07:24,010 manufacturing facility at Huntington 156 00:07:29,400 --> 00:07:26,890 Beach California following installation 157 00:07:31,410 --> 00:07:29,410 in beta test stands number one the stage 158 00:07:34,430 --> 00:07:31,420 underwent pre firing checkout in 159 00:07:38,040 --> 00:07:34,440 preparation for its acceptance firing on 160 00:07:40,650 --> 00:07:38,050 July 29th a successful acceptance firing 161 00:07:42,990 --> 00:07:40,660 was conducted following data evaluation 162 00:07:44,970 --> 00:07:43,000 the stage was removed from the stand for 163 00:07:47,640 --> 00:07:44,980 post firing checkout in the vertical 164 00:07:52,590 --> 00:07:47,650 checkout lab turn over to NASA is 165 00:07:54,840 --> 00:07:52,600 expected in late September factory 166 00:07:57,300 --> 00:07:54,850 checkout of the third flight stage began 167 00:07:59,940 --> 00:07:57,310 in late July at Huntington Beach with 168 00:08:02,250 --> 00:07:59,950 completion due in September and shipment 169 00:08:06,000 --> 00:08:02,260 to SEC toe in October for acceptance 170 00:08:08,190 --> 00:08:06,010 testing structural fabrication and 171 00:08:10,170 --> 00:08:08,200 assembly is continuing on the fourth and 172 00:08:15,270 --> 00:08:10,180 fifth flight stages at Huntington Beach 173 00:08:17,640 --> 00:08:15,280 and a DEA seized santa monica plant the 174 00:08:19,650 --> 00:08:17,650 high force vibration test program was 175 00:08:21,840 --> 00:08:19,660 begun in June and continued throughout 176 00:08:24,180 --> 00:08:21,850 the quarter at the Thiokol chemical 177 00:08:27,120 --> 00:08:24,190 corporations watch division near Brigham 178 00:08:29,220 --> 00:08:27,130 City Utah purpose of the program is to 179 00:08:31,590 --> 00:08:29,230 provide information regarding the low 180 00:08:34,410 --> 00:08:31,600 frequency sensitivity of major weight 181 00:08:45,870 --> 00:08:34,420 carrying structures testing is scheduled 182 00:08:51,720 --> 00:08:49,079 in June the two f-1 engines destined for 183 00:08:52,379 --> 00:08:51,730 use in the quad 2 test program later in 184 00:08:54,809 --> 00:08:52,389 the quarter 185 00:08:57,749 --> 00:08:54,819 came off rocky dines production line at 186 00:08:59,730 --> 00:08:57,759 its Canoga Park California plant while 187 00:09:02,430 --> 00:08:59,740 two configuration engines are those 188 00:09:04,740 --> 00:09:02,440 qualified for manned flight reliability 189 00:09:07,319 --> 00:09:04,750 and designed to meet the additional 190 00:09:12,059 --> 00:09:07,329 payload requirements of the 4th Saturn 5 191 00:09:14,400 --> 00:09:12,069 and subsequent vehicles at 1/4 retinas 192 00:09:16,199 --> 00:09:14,410 evaluation review held in Rocketdyne in 193 00:09:18,210 --> 00:09:16,209 June it was determined that 194 00:09:20,759 --> 00:09:18,220 qualification testing would begin in 195 00:09:23,490 --> 00:09:20,769 August at the rocket engine test site at 196 00:09:27,030 --> 00:09:23,500 Edwards California to prove engine 197 00:09:29,009 --> 00:09:27,040 performance and design parameters the 198 00:09:32,069 --> 00:09:29,019 first in the series of firings was held 199 00:09:32,699 --> 00:09:32,079 on August 1st the program is expected to 200 00:09:35,220 --> 00:09:32,709 be finished 201 00:09:37,860 --> 00:09:35,230 during September one engine is being 202 00:09:40,290 --> 00:09:37,870 used for safety limits testing and the 203 00:09:42,210 --> 00:09:40,300 other for duration testing requiring a 204 00:09:52,590 --> 00:09:42,220 total of two thousand two hundred fifty 205 00:09:54,569 --> 00:09:52,600 seconds firing time the quoi to test 206 00:09:58,769 --> 00:09:54,579 series for a qualification of the 207 00:10:01,410 --> 00:09:58,779 upgraded 230,000 pounds thrust j2 engine 208 00:10:03,900 --> 00:10:01,420 was initiated by Rocketdyne in early 209 00:10:06,780 --> 00:10:03,910 August and in Santa Susana California 210 00:10:09,389 --> 00:10:06,790 test site testing will continue next 211 00:10:14,069 --> 00:10:09,399 quarter the series will comprise 30 212 00:10:16,620 --> 00:10:14,079 tests totaling 3750 seconds an R&D 213 00:10:19,920 --> 00:10:16,630 program simulating the form of Wow - 214 00:10:22,319 --> 00:10:19,930 testing was completed in July with 34 215 00:10:24,090 --> 00:10:22,329 firings performed for a total of four 216 00:10:27,990 --> 00:10:24,100 thousand three hundred thirty-five 217 00:10:29,850 --> 00:10:28,000 seconds at the air force's Arnold 218 00:10:32,009 --> 00:10:29,860 engineering development center at tella 219 00:10:35,040 --> 00:10:32,019 home at Tennessee the first in a series 220 00:10:38,309 --> 00:10:35,050 of j2 engine environmental verification 221 00:10:40,620 --> 00:10:38,319 test firings was held on August 27th 222 00:10:42,509 --> 00:10:40,630 after successful completion of several 223 00:10:45,840 --> 00:10:42,519 months efforts to overcome all problems 224 00:10:48,150 --> 00:10:45,850 of environmental control the test 225 00:10:51,210 --> 00:10:48,160 program is presently planned to extend 226 00:10:53,550 --> 00:10:51,220 through June 1967 with an estimated 227 00:10:56,040 --> 00:10:53,560 three firings per month including 228 00:10:59,550 --> 00:10:56,050 several altitude restarts of the engine 229 00:11:01,739 --> 00:10:59,560 the huge test cell largest of its type 230 00:11:05,550 --> 00:11:01,749 can simulate altitude and thermal 231 00:11:08,340 --> 00:11:05,560 environment at 125,000 feet about 25 232 00:11:10,889 --> 00:11:08,350 miles tests will duplicate conditions of 233 00:11:20,579 --> 00:11:10,899 the j2 on the ground and during boost 234 00:11:22,920 --> 00:11:20,589 first burn Coast and second burn ground 235 00:11:24,769 --> 00:11:22,930 testing of Saturn 5 instrument units 236 00:11:26,670 --> 00:11:24,779 moved into its final phases 237 00:11:29,519 --> 00:11:26,680 environmental tests on the flight 238 00:11:31,679 --> 00:11:29,529 systems I you were completed August 10th 239 00:11:34,769 --> 00:11:31,689 at Douglas aircrafts Huntington Beach 240 00:11:37,230 --> 00:11:34,779 facility the IU was mated to a third 241 00:11:39,360 --> 00:11:37,240 stage forward stage simulator and a 242 00:11:41,939 --> 00:11:39,370 lunar module thermal simulator for the 243 00:11:45,869 --> 00:11:41,949 tests which simulated orbital thermal 244 00:11:47,910 --> 00:11:45,879 vacuum conditions testing of the third 245 00:11:50,069 --> 00:11:47,920 structural test I you which was 246 00:11:52,829 --> 00:11:50,079 delivered to Marshall by IBM Huntsville 247 00:11:56,090 --> 00:11:52,839 in June got underway in mid-august with 248 00:11:59,309 --> 00:11:56,100 completion scheduled early next quarter 249 00:12:02,519 --> 00:11:59,319 check out of the first Saturn 5 flight I 250 00:12:04,619 --> 00:12:02,529 you was finished by IBM on August 19th 251 00:12:08,460 --> 00:12:04,629 and the unit was shipped to Kennedy 252 00:12:10,679 --> 00:12:08,470 Space Center on August 25th structural 253 00:12:12,990 --> 00:12:10,689 fabrication and component installation 254 00:12:15,389 --> 00:12:13,000 for the second flight hi you have been 255 00:12:23,509 --> 00:12:15,399 finished by IBM and check-out is in 256 00:12:28,559 --> 00:12:26,309 at Marshalls Mississippi test facility 257 00:12:30,929 --> 00:12:28,569 construction continued on second stage 258 00:12:33,600 --> 00:12:30,939 static tests and number two designated 259 00:12:36,569 --> 00:12:33,610 a1 with brick and mortar work over 80% 260 00:12:39,299 --> 00:12:36,579 finished direction of Steel for the load 261 00:12:41,129 --> 00:12:39,309 platform is essentially complete and the 262 00:12:43,799 --> 00:12:41,139 engine removal platform has been in 263 00:12:45,329 --> 00:12:43,809 placed piping for the water manifolds 264 00:12:48,269 --> 00:12:45,339 and the flame deflector is being 265 00:12:50,340 --> 00:12:48,279 installed installation of conduit and 266 00:12:52,639 --> 00:12:50,350 wiring for technical systems is in 267 00:12:54,780 --> 00:12:52,649 progress above the seventh floor level 268 00:12:57,989 --> 00:12:54,790 construction of the stand is scheduled 269 00:13:01,160 --> 00:12:57,999 for completion early in 1967 with 270 00:13:03,989 --> 00:13:01,170 activation due by the middle of the year 271 00:13:06,150 --> 00:13:03,999 the center pier of the duo position 272 00:13:08,819 --> 00:13:06,160 first stage static test stand is 273 00:13:11,189 --> 00:13:08,829 structurally complete installation of 274 00:13:13,500 --> 00:13:11,199 partitions insulation of water lines and 275 00:13:15,090 --> 00:13:13,510 touch-up painting are in progress 276 00:13:17,760 --> 00:13:15,100 elements of the ground support equipment 277 00:13:21,870 --> 00:13:17,770 have been installed and check out in the 278 00:13:23,880 --> 00:13:21,880 manual mode is underway the stands be 279 00:13:26,190 --> 00:13:23,890 one position made steady progress during 280 00:13:28,620 --> 00:13:26,200 the quarter fabrication of the mounting 281 00:13:32,670 --> 00:13:28,630 ring support structure rolling deck and 282 00:13:34,530 --> 00:13:32,680 engine removal platform is underway the 283 00:13:36,330 --> 00:13:34,540 stands be to position the first 284 00:13:39,210 --> 00:13:36,340 scheduled for completion is well 285 00:13:41,310 --> 00:13:39,220 advanced before hold down arms and 286 00:13:43,980 --> 00:13:41,320 actuators were installed this quarter 287 00:13:46,020 --> 00:13:43,990 the engine removal platform and rolling 288 00:13:48,080 --> 00:13:46,030 deck are complete and finished work on 289 00:13:50,880 --> 00:13:48,090 the flame deflector is well underway 290 00:13:53,310 --> 00:13:50,890 piping for the liquid oxygen system is 291 00:13:55,170 --> 00:13:53,320 in progress and installation of conduit 292 00:13:58,340 --> 00:13:55,180 and wiring for technical systems 293 00:14:02,580 --> 00:13:58,350 throughout the position is also underway 294 00:14:04,530 --> 00:14:02,590 in summary June July and August 1966 295 00:14:07,200 --> 00:14:04,540 were months of steady achievement along 296 00:14:09,420 --> 00:14:07,210 a broad front of activity flight stages 297 00:14:12,210 --> 00:14:09,430 for the first saturn v flight vehicle 298 00:14:14,280 --> 00:14:12,220 have now all been delivered to KSC with 299 00:14:16,170 --> 00:14:14,290 the exception of the second stage which 300 00:14:20,190 --> 00:14:16,180 is being readied for acceptance firing 301 00:14:22,110 --> 00:14:20,200 at MTF manufacturing of subsequent 302 00:14:24,840 --> 00:14:22,120 flight stages is continuing at the 303 00:14:27,480 --> 00:14:24,850 various contractor plants and grounds 304 00:14:30,260 --> 00:14:27,490 tests of engines stages and instrument